Home additions are one of the most effective ways to expand your living space and increase your home’s value — without moving. Every addition we build is fully custom, designed to match your home’s existing architecture and your family’s lifestyle. We handle everything from planning and permitting to construction and finishing.
Addition Progress Videos
Browse our addition project updates and see how L3 Construction brings new living spaces to life. From foundation to finishing touches, our weekly video updates give you a behind-the-scenes look at the progress and craftsmanship that go into every addition we build.
Week 13
This home has a fully functional kitchen and living space ready to enjoy! Next up – painting! Seeing a space come together in time for moments like this is what it’s all about.
Week 12
Cabinets are fully installed, countertops are in, electrical finals are underway, backsplash is about to begin, and millwork is in progress tying everything together.
Week 11
This week has some major milestones! Cabinet installation is underway, flooring and millwork are going in, and countertops are being installed with backsplash starting today.
Week 10
This week, the structure tie-in is happening, creating a seamless connection between the existing home and the new addition. Inside, drywall is up, and taping is underway!
Week 9
This week is about prepping the inside of the addition for the next big steps. Insulation is installed and the vapor barrier is in — creating a comfortable, energy-efficient envelope for the new space.
Week 8
Week 7
The windows are in, and HVAC work is underway! Chip gives a walkthrough inside showing the new ductwork and how the interior layout is starting to take shape.
Week 6
This week’s big milestone — the roofing is complete! We re-roofed the entire home, not just the addition, to ensure a seamless look and long-lasting protection.
Week 5
Framing is nearly complete, and this addition is really starting to come to life! Next week windows are going in, siding and roofing underway, and patio doors being installed.
Week 4
The ICF foundation walls are in place! Chip walks us through what that means and how these insulated concrete forms create a strong, energy-efficient foundation for the new addition.
Week 3
The sewer tie-in to the septic system is finished and getting ready to start setting the ICF foundation blocks. ICF (Insulated Concrete Forms) is a system that combines strength, energy efficiency, and durability.
Week 2
Demo and ground breaking started today. Big changes are underway — check it out! Follow along each week as we share updates on this addition project.
Week 1
We’re kicking off an exciting addition project this week — and we’re bringing you along for the journey! We’ll be sharing progress updates, behind-the-scenes details, and what’s coming up next.